SPIRAC is proud to be part of the ongoing upgrade at the Rouse Hill Wastewater Treatment Plant, delivering advanced sludge storage and handling solutions to support efficient operations.
Scope of Work:
- Two sludge silos (140m³ each)
- Two SPIROLINE® U420 Silo Cross Conveyors
- Two SPIROLINE® U420 Silo Loading Conveyors
- Four SPIROLINE® U420 Silo Base Outloading Conveyors
- One SPIROLINE® U620 Truck Loading Conveyor
- Two Sliding Frame Systems SFR 7500
These systems are designed to ensure reliable sludge transfer, optimized storage, and smooth outloading for improved plant performance.
Check out this video of the installation: https://www.youtube.com/watch?v=N-ea2dGkvhQ
We’re excited to see this project progress and will share more updates as we move closer to completion.